- Revision
- 01 · Dec 4, 2026
- Approver
- M. Rivera · Project Manager
- Status
- W1 released · W2 pending
Open · Q-01
Confirm tenant access for W2
- Owner
- M. Rivera · confirm with building management
- Deadline
- Mon, Dec 7 · 2 p.m. local
- Decision & consequence
- Release in writing once confirmed. If unresolved, keep the hold and pull W2 from Tuesday’s plan.
Source record
- S-01 · Accepted scope · Nov 25
- W1 and W2 marked walls only. Doors, trim, floors, and ceilings excluded.
- A-01 · Site access note · Dec 2
- W1 hours, west loading-door staging, and occupied corridor restrictions.
- P-01 · Approved schedule · Dec 3
- W1 Monday morning. Tuesday W2 slot conditional on written access release.
- Q-01 · Open item · Dec 4
- Tenant access for W2 remains unconfirmed.